|
|
|
Reverse Circulation Drilling Used On Micropiles
Richmond San Rafael Bridge
(click here to download a
printable version)
By: John H. Berry, P.G.
Hydrogeologist/CETCO Drilling Products
San Francisco, California - Unique drilling procedures were developed
by AGRA Foundation, Inc., (AGRA) of Richmond, California, for the
seismic retrofit of foundation elements on the Richmond San Rafael
Bridge. The bridge, which spans the northern portion of the San
Francisco Bay, extends from Contra Costa on the east to Marin Counties
on the west. The project entails installing high-capacity micropiles
through existing concrete belled piers supported on H-piles. A total of
31 two-bell piers will be retrofitted. Between 12 and 32 micropiles will
be installed at each pier (6 to 16 micropiles per bell). AGRA also is
installing 66-inch and 150-inch-diameter end-bearing piles at select
locations. The California Department of Transportation (Caltrans) is the
bridge owner and the designer of the retrofit elements. Tutor-Saliba-Koch-Tidewater
Joint Venture is the Prime Contractor on this project. Project
completion is scheduled for December 2003.

Drill platform with drill rig. (click image to enlarge) |

Slurry Cleaning Tank with Desander.
(click image to enlarge |

View of the Richmond San Rafael Bridge. (click image to enlarge) |

Bridge with view of Drill Platform
and Barges (click image to enlarge) |
AGRA’s drilling equipment, slurry system, support equipment, and
supplies are situated on prefabricated work platforms installed around
existing bridge piers. A prefabricated steel template is installed at
each pier prior to work platform installation. Precise placement of the
templates is necessary to guide coring and drilling equipment through
the existing reinforced concrete bells and between the existing H-piles
that support the bells.
Drilling Method
Reverse circulation drilling with dual wall drill rods is used to
advance through alluvium and bedrock. At the beginning of the drilling
process, a temporary 20-inch-diameter conductor casing is extended from
the work platform deck to the top of the concrete bell. The concrete
bell is cored after which a permanent 12-inch-diameter casing is lowered
through the cored bell to mudline. Drill rods equipped with a tricone
bit are advanced through the permanent casing to the mudline. The bit
and permanent casing are advanced in tandem through alluvium (consisting
of scour protection, Bay Mud, sand, and clay) to Franciscan Formation
bedrock, thereby casing off alluvium from bedrock and the micropile rock
socket. Permanent casing is seated in the Franciscan Formation which
consists primarily of interbedded graywacke sandstone and shale of
highly variable rock quality. The micropile rock socket is then drilled
by advancing the drill rod and tricone bit beyond of the tip of the
permanent casing using synthetic slurry as drill fluid. As a rock socket
is advanced, a constant head of drilling slurry is maintained. Once a
rock socket is completed, the synthetic slurry inside the socket is
replaced with fresh slurry to help maintain the integrity of the socket
between the time that socket drilling is completed and the micropile is
grouted. AGRA is using Shore Pac GCV synthetic slurry by CETCO to meet
the viscosity and pH requirements of the contract specifications.
Slurry Closed System
A closed circulation system is used to advance through alluvium and
bedrock. Clean drill slurry is introduced into the system at the drill
head at a rate of about 13 gallons per minute. The resulting slurry/air
mix flows through continuous air channels located in the wall of the
drill rod. The air channels extend from the drill head (at deck level)
to discharge ports located about 12 inches above the top of the tricone
bit. A metal “skirt” above the discharge ports prevents backwash of
slurry up the annular space between the rock socket wall and the drill
rods. Drill cuttings are carried up the center of the drill rod to a
hopper located on the work platform deck. “AGRA is responsible for
slurry QA/QC and associated documentation.” says Bob Bishop, AGRA’s
drilling superintendent. “It is important to maintain viscosity and pH
parameters and also keep the Shore Pac slurry under a constant pressure
head to prevent air from coming up the annular space between the rock
socket wall and the drill rod.”
Slurry Recycling & Usage
Shore Pac slurry is stored in three 4,000 gallon dedicated slurry
tanks located below the deck of a work platform. One tank is used for
recycled slurry and two are kept full of fresh slurry. Stored slurry is
pumped via hose to the drill head of the CMV MK 1200 DT drill rigs that
AGRA is using on this project. A return hose conveys slurry with rock
cuttings from the rock socket into a cyclone de-sander elevated above a
dual wall cuttings tank. Weirs on the inner wall of the cuttings tank
allow slurry to flow out of the inner chamber containing the cuttings
and into a perimeter chamber, thereby isolating solids from slurry
fluid. The spent slurry is then pumped back into one of the dedicated
holding tanks beneath the work platform deck where it is “built up” and
retested prior to reuse. Locating the tanks below the platform deck
allows for more work space for personnel, cranes, drill rigs, and
supplies. Work space is at a premium as fully equipped platforms allow
for about 8,000 square feet of useable space. According to Mr. Bishop,
“Because of the environmental sensitivity of this high profile project,
and the logistics of moving drilling spoils to land, we chose a drilling
slurry that could be recycled and would generate relatively dry spoils.”
|