Broad River & Che Che Ssee River Bridge Project
(click here to download a
printable version)
CETCO Drilling Products (Foundation Drilling)
Beaufort, South Carolina
By John H. Berry P.G., CETCO Foundation Division Manager

Digging Bucket used for loose sands and oyster
shells. (click image to enlarge) |
Construction on the bridges across many rivers in the low country of
South Carolina has been needed for along time. As with 90% of our
nations’ bridges, these bridges have deteriorated from salt corrosion
and age. Outdated for today’s heavy traffic, the bridges will slowly
need to be replaced. Funds for this construction have been appropriated
and work has started in South Carolina beginning with the Broad River &
Che Che Ssee River Bridge. These rivers empty into the Atlantic Ocean
just north of Savannah, Georgia.
What makes this project special is that CETCO Drilling Products has
accomplished what has never been done before, approval by The Department
of Transportation of South Carolina to use synthetic dry polymer as
drilling slurry for construction of foundation piers to support this new
bridge. Until now when foundation drilling within saltwater was
required, Attapulgite clay has always been used.

Crane Mounted drilling attachment allows deeper holes to be drilled.(click image to enlarge) |
The CETCO product being used instead of Attapulgite is Shore Pac®.
The general contractor for the Broad River & Che Che Ssee River Bridge,
Balfour Beatty Construction, chose Shore Pac® because it offered an
environmentally safe slurry that could be recycled and could be mixed
using the saltwater from the Broad River as the mix water.
The Broad River is South Carolina’s best fishing river. Strict
guidelines were imposed by the Department of the Environment that no
polymer slurry was to be spilled into the waters of the Broad River.
CETCO®’s product had acquired an extensive resume of data when approved
by the State of California Department of Transportation. This made the
State of South Carolina and the general contractor, Balfour Beatty,
comfortable with using a tried and proven product.
This bridge project consisted of 156 foundation caissons across both
rivers. Each shaft is 96” in diameter and 120’ deep. The shafts are
together in pairs. After each pair is drilled with slurry and poured
with concrete the barges move on to the next location. Work was in close
quarters on three barges floating in the river. A casing 60’ long is set
into the marl clay on the bottom of the river. This casing is supported
by a platform. The shaft is drilled within the casing down to tip point
of 120’. The Shore Pac® slurry holds the sidewalls of the large diameter
hole open. The polymer slurry also cohesively binds the spoils onto the
flights of the drilling auger helping with removal and advancement of
the caisson. When the hole is finished, a rebar cage is placed into the
shaft. Next concrete is poured into an (elephant trunk) tremie pipe. As
the concrete fills the foundation shaft the slurry is displaced and
pumped back into a holding tank for re-use.
CETCO Drilling Products Shore Pac® reduces overall cost of
construction by saving time and money. Balfour Beatty Construction will
saved over $200,000 in material costs alone by using the Shore Pac®
polymer slurry system. The monies saved by completing the project ahead
of schedule will be measured in many other ways. The construction
industry, especially the Department of Transportation may adjust to new
methodology slowly, however, when a new technique is proven the legend
moves quickly along the grapevine.
 |
 |
| Slurry tanks on the barge
next to the drilling barge. These tanks hold recycled
slurry and fresh mixed batches of Shore Pac slurry.
(click image to enlarge) |
View of the old bridge & the rebar cage that
is inserted into the drilled shaft prior to pouring
concrete.
(click image to enlarge) |
|