|
|
|
Drop & Ventilation Shaft Excavation for a Combined Sewer Overflow (CSO) Abatement Plan
(click here to download a
printable version)
Narragansett Bay Commission (NBC), Providence, Rhode Island
Introduction: The Narragansett Bay Commission (NBC) proposed
the construction of seven underground facilities and three deep rock
tunnel segments. The underground storage tanks and tunnels would contain
the sewerage overflows during rain events so that the sewage could be
returned to the system for treatment after the storm. The Drop Shaft and
ventilation Shaft needed to be drilled to intersect the tunnel at an
exact elevation located approximately 208 feet under the City of
Providence, Rhode Island. The site location was located 20-feet from the
western edge of the Providence Warf. The area was once a coal dock. A
combination method of Foundation drilling under Shore Pac slurry to
bedrock then switching to reverse circulation drilling through the
bedrock was utilized by Case Foundation to excavate the drop and
ventilation shafts.
The Phase I of the Combined Sewer Overflow (CSO) Abatement Program
consisted of a storage tunnel in rock connected to a near-surface
collection system by drop shafts. The tunnel begins near NBC’s Field’s
Point Wastewater Treatment Facility, travels north along the Providence
River, turns west to follow the Woonasquatucket River, and ends near
Calverly Street. Sixteen-thousand feet long, 26 feet in diameter, and
220 to 280 feet underground, the Tunnel will hold over 60 million
gallons of combined sewage. It will reduce the annual volume of CSO
discharges by approximately 40 %, and is expected to reduce shell
fishing closures by 47% in the northern half of the Upper bay, and 77 %
in the southern half.
Combined Sewer Overflow (CSO): At the turn of the century most urban
areas across the nation built sewer systems to carry storm water and
sewage in the same pipe. This is called a combined sewer. During dry
weather conditions the combined sewer works fine. But during heavy rain
storms these combined flows frequently exceed their capacity into the
sewer system and overflow into local rivers and the Narragansett Bay.
The combined sewer overflows into the bay are a violation of the Federal
Clean Water Act that regulates polluted discharges from industries and
sewer treatment plants into public waterways. According to the Clean
Water Act, it is the objective for rivers, lakes, bays, and other water
bodies throughout the country to be fishable. Each year the 66 CSOs in
the NBC district release an estimated 2.2 billion gallons of untreated
combined sewage into the Narragansett Bay and its tributaries, namely
the Blackstone, Moshassuck, Providence, Seekonk, Woonasquatucket, and
West Rivers. CSO’s pose pollution and public health risks, the sewage
comprises residential, commercial and industrial wastes, and other
pollution washed or dumped into drains. These overflows carry pollutants
in the form of sewage solids, metals, oil, grease, and chemicals which
can affect the health of those who swim in CSO polluted water or eat
shellfish contaminated with these materials. To protect human health in
Rhode Island, certain areas of the bay are permanently closed to shell
fishing, and over 11,000 acres are temporarily closed for harvesting
when there is more than one-half inch of rainfall.
(click image to enlarge)

Shore Pac Drilling Slurry: CETCO Drilling Products supplied
the polymer drilling slurry Shore Pac that was utilized by the Drilled
Shaft contractor Case Foundation out of Roselle, Illinois. Case
Foundation had the job of drilling a 14-feet inside diameter, 208 –feet
deep drop shaft from the surface, and a 5-feet inside diameter, 206 foot
deep, ventilation shaft. The function of the Shore Pac was to hold the
holes open while Case Foundation drilled down to bedrock and inserted a
permanent 14-foot casing for the drop shaft and a 5-foot casing for the
ventilation shaft set into bedrock. At times during the drilling the
Shore Pac slurry had to remain in the open borehole for up to two weeks
as old wharf wood pilings were removed slowly from the borehole. “On top
of the old vertical wharf piling the soil was impacted with various
contaminates that effected the viscosity of the Shore Pac slurry, we
kept strengthening the Shore Pac until the casing liner could be
installed” said Nick Puglia. At approximately 7 feet below land surface
wooden piles measuring 8-10 –inches in diameter in the shape of an X
were encountered. The wooden piles were rotten at the top, but as soon
as groundwater was reached at 17-feet below land surface the wooden
piles were solid.
The soil consisted of rubble and fill material at the surface,
changing to brown gray moist stiff silt and clay for 50 feet, and then
silty coarse sand with gravel on top of the weathered shale bedrock was
encountered. The weathered shale located approximately 90 feet below
land surface had to reached with the slurry alone holding the 14-foot
diameter hole open.
The Drop and Ventilation Shaft Construction: Had to be completed
exactly according to within 6-inches of the specified location. This
milestone was essential for the installation of the dear ration chamber
by the tunneling boring contractor. According to the site drilling
superintendent Nick Puglia of the Case Foundation Broomall, Pennsylvania
office who said “try drilling a 14-foot diameter shaft with an auger to
bedrock at 90 feet below land surface under Shore Pac slurry, then
switch to reverse circulation drilling for the remainder of the borehole
and stop within 6-inches at 202 feet below land surface. Then seal the
shaft to allow the safe progression of the underground tunnel boring
work to intersect the shaft. It wasn’t easy.” Case Foundation used a
Manitowoc 2250 Crane with a Call weld 200 drilling attachment to drill
the top portion, for the reverse circulation portion Case partnered with
Steven M. Hain of Garland, Texas.
Tunnel Boring: The tunnel boring contractor was a joint venture
between M L Shank and Balfour Beatty Construction Company. The
six-hundred-ninety ton tunnel boring machine was constructed in Japan
and shipped to Providence, RI. The tunnel boring machine was used to
make the 3 mile long 26 feet in diameter 250 foot deep CSO tunnel. The
tunnel boring machine consists of the main body and the cutter head. The
cutter head is attached to the main body (the shield) by a specially
designed boring shield that performs a number of functions. It houses
the motors which rotate the cutter head, and the thrust cylinders which
provide the forward thrust on the cuttings discs. Because the motors are
turning the cutter head, the shield must also resist the opposite forces
which are trying to pull the shield in the opposite direction.
Another function of the shield is to protect the workers who are
installing the initial tunnel support behind, or inside of the TBM. The
main spine tunnel is supported by precast concrete rings assembled
inside of the shield, then expanded to fit the tunnel excavation as the
shield moves forward the rings come out of the tail. Hydraulic ring
erectors are mounted inside the shield and are used to lift and build
the rings.
Once a 4-foot long ring is built, the thrust rams push against the
leading edge of the ring, propelling the shield and cutter head forward.
During the push, the cutter head is rotated, rolling the disc and
crushing the rock. The rock chips, called muck, are scooped into the
cutter head through a bucket head as it rotates. The muck is dumped onto
a conveyer, inside the cutter head that carries the muck through the
shield and into the supported tunnel where it is loaded into rail cars
and transported out of the tunnel.
|